Letters containing further information about the upcoming road resurfacing works are being delivered to residents today.
According to the information provided by BANES, the works will take place in three phases:
Phase 1 – Holcombe Vale: approximately 2 days
Phase 2 – Holcombe Close & The Chestertons: approximately 3 days
Phase 3 – Holcombe Lane & Downside Close: approximately 4 days
The timings are estimates and may change depending on progress and circumstances on site.
The letter provides further information about the works, including arrangements for access and parking and the works themselves. A copy of the letter can be found on the Parish Council Facebook page here: Bathampton Parish Council | Facebook
There will inevitably be some disruption while the work is being carried out, and we appreciate residents’ patience and understanding. We hope the completed works will result in much better safer road surfaces across these areas.
Please share with neighbours who may not have seen the information or received the letter yet.